First page of the original plans
First page of the original plans
First page of the original plans

MiniCoupe Builders Log

N853WD

Builder: Bill Day, PMP
Started 11/1/2003

Last update 12/27/2008

Jump to Pictures

Limited Number of Pictures (For Slower Connections)
Am I flying yet?
11/01/2003 Started cutting up my Teenie Two, it was damaged from Isabel. I had a lot of stuff in the storage area collapse on it
  Put wing spars together. Can't find my notes as to when I did what with the spars and other pieces I have cut out and cleaned up.
10/11/2003 Cutting out nose ribs and main ribs
02/14/2004 Finished riveting the center section spar. Need to drill holes for all the attachments and fuse angles.
02/16/2004 Cut side panels from 8525K134/McMaster for joystick setup. Drilled holes for angle attachment and circular pieces. Misaligned one set of holes, offset by 1/2" and drilled another set. Got hold of scrap tubing 1 7/8" as the the center part, cut to 5". Cut 1" x 1" x 1/8" angles for connection to center spar.
02/17/2004 Cut slot in joystick setup tube.
02/21/2004 Replacing pulled rivets with solid rivets
02/22/2004 Finished replacing pulled rivets with solid rivets, saved several pounds for each spar. Blocked up center section and leveled. Inserted outer wing spars, one at a time, and set deherial. Drilled and then reamed for taper pins. Need to get a #9 reamer to complete the taper, #8 not big enough.
02/28/2004 Finished control system setup. Took over to let Ron Dixon see it and he approved of its construction. Cut and drilled F-1s and clecoed to center section.
02/29/2004 Started working on the right wing and drilling main ribs for spar. Finished and put spar into center section and took pictures.
03/03/2004 Started working on nose ribs only got 5 done.
03/12/2004 Finished working on nose ribs.
04/17/2004 Started working on left main ribs to left spar
04/18/2004 Finished drilling main and nose ribs to left spar
05/01/2004 Bent Wing Skins for Right and Left wings. Bent both ailerons.
05/06/2004 Cut 4130 Tubing for main landing gear.
05/08/2004 Picked up engine and 30' of hinge material.
05/12/2004 Started drilling right main ribs to bottom wing skin.
05/15/2004 Continued drilling right main ribs to bottom wing skin. Worked on tapping 1/2" tubing for rod bearings.
05/16/2004 Finished drilling right main ribs to bottom skin. Finished aileron control horn. Setup one end of aileron control rods. Installed rear wing attache bracket.
05/17/2004 Bend right rear spar support. Drilled and clecoed to rear spar. Cut out doubler and door for aileron control access.
05/19/2004 Cut and driled one half of the aileron hinge.
05/23/2004 Cut and bent aileron rib. Put together the micro-stop counter sink and adjusted it. Took some pictures of current work.
05/24/2004 Cut and bent aileron rib. Started moving everything into basement, more room to work.
05/25/2004 Pulled wing apart and started deburring everything.
05/26/2004 Completed deburring and dimpled bottom of main ribs and bottom skin. Countersunk lower spar holes.
05/30/2004 Cleaned painting attempt from bottom skin. Started working on removing aileron's paint job.
05/31/2004 Put Main Ribs and bottom skin back together. Drilled a few more holes for the rear spar. Measured and marked top sheet for cutting. Still working on aileron paint.
06/01/2004 Finished aileron paint. Cut and started drilling the top skin.
06/02/2004 Almost finished drilling the top skin. Just have main spar section to drill. Worked on hinge area for free movement.
06/03/2004 Finished drilling the top skin.
06/05/2004 Built benting brake for nose skin. Bent skin and placed on wing.
06/08/2004 Started trimming Nose skin and seting up drill guide lines.
06/09/2004 Put bend in nose skin where it does not belong. Wing slid off table and bent back rear spar. Asked Bobby Thomas (Technical Counselor)to come take a look at it Saturday.
06/22/2004 After having Bobby show me how to repair everything I still decided to replace the nose ribs and skin. So I redid the nose ribs and bent another skin. Got all the holes drilled and clecoed inplace. Now I can rivet the nose section. I also placed the rubber gomments in the the ribs and have a piece of ice maker tubing to place in after riveting. The tubing is for wiring support.
06/27/2004 Started riveting the nose skin. The rivet gun started acting up, so quit for the day.
06/28/2004 Pulled the rivet gun apart and cleaned it. Found one piece was put in wrong (got it that way off ebay), now it seems like new. Finished riveting the nose piece.
06/30/2004 Trimmed nose section to fit to the spar. Drilled hinge area on aileron.
07/01/2004 Deburred and dimpled aileron hinge holes. Riveted aileron. Attached aileron to wing to start working on the length of the push rod.
07/03/2004 Installed push rod mount on aileron. Completed push rod. Mounted aileron control to main spar. Cleaned up hinge area to eliminate the squeaks.
07/05/2004 Dimpled ribs and top skin. Started closing up wing. Waiting for some longer rivets for the spar. Completed top skin to ribs.
07/11/2004 Started working on the left wing. Marking up bottom skin for rib placement.
07/13/2004 Riveted top main spar on right wing. Now the fun begins, ready to rivet bottom skin and rear spar.
07/14/2004 Riveted bottom main spar on right wing. Done 1/4 of the bottom skin.
07/16/2004 More riveting on bottom skin.
07/17/2004 Closed Right Wing! Need to finish access panel, wiring and wing tip. Started drilling left bottom skin for ribs.
07/31/2004 Finished access panel, just need opening mechanism installed.
08/01/2004 Drilled ribs for bottom skin and rear spar. Started working on pitot mounting setup.
08/09/2004 Completed pitot mounting setup.
08/11/2004 Worked on aileron control setup
08/11/2004 Finished aileron control setup.
08/13/2004 Started cutting out new nose ribs for left wing. See Right Wing log entries.
08/14/2004 Finished cutting nose ribs. Bent nose ribs to shape and drilled for spar.
08/15/2004 Cleaned up and cut lighting hole in nose ribs. Flanged nose ribs.
08/18/2004 Drilled nose ribs for spar
08/19/2004 Cut old aileron apart, stress cracks in trailing edge, will use part of it for rear spar doubler.
08/20/2004 Cleaned up rear spar doubler and started drilling.
08/21/2004 Completed rear spar doubler
08/29/2004 Started working on top skin, cut to size.
08/31/2004 Drilled top skin.
09/01/2004 Cleaned up top skin, ribs and main spar.
09/04/2004 Worked on rear spar connection support. Started riveting rear spar doubler, ran out of rivets.
09/06/2004 Worked on access holes for aileron control and pitot/static system. Have doublers cut out and drilled. Have access hole for pitot/static.
09/07/2004 Dimpled and riveted doubler for pitot/static access hole.
09/18/2004 Finished riveting rear spar doubler. Bent new left aileron and center trailing edge.
09/20/2004 Marked aileron for rivet spacing and hinge size.
09/21/2004 Drilled and deburred aileron.
09/22/2004 Drilled and deburred hinge on aileron side.
09/25/2004 Started working on aileron ribs. Nothing wants to fit right.
09/26/2004 Completed all the ribs for the aileron, drilled, deburred, dimpled and riveted ribs.
09/27/2004 Dimpled hinge area on aileron and riveted hinge in place. Started putting wing together to work on the wing side of the hinge.
09/29/2004 Setup and drilled aileron hinge on wing side.
09/30/2004 Bent the nose skin and positioned on wing. Ready to finish setting up and drilling rivet holes.
10/02/2004 Drilled rivet holes in nose skin. Dimpled and riveted nose skin to nose ribs.
10/03/2004 Sized aileron push rod. Cleaned up hinge area for aileron. Countersunk the rear spar doubler angle. Dimpled the top skin and half the ribs
10/05/2004 Riveted ribs to top skin. Dimpled the spar line on the nose unit. Will take pictures tomorrow (6th Oct).
10/06/2004 Riveted ribs to main spar. Riveted top skin to spar and nose section.
10/07/2004 Completed dimpling the bottom skin and aileron hinge. Put skin into place, ready to rivet.
10/08/2004 Completed left wing!
10/10/2004 Drilled and bolted F1s to center spar. Drilled and bolted CS-33s to center spar.
10/12/2004 Started cleaning up main ribs
10/13/2004 Finished main ribs and drilled landing gear attachment angles for left side.
10/15/2004 Drilled landing gear attachment angles for right side.
10/16/2004 Drilled and bolted CS-6s to main spar. Started riveting CS-12s to ribs.
10/18/2004 Finished the ribs. Started drilling for ribs to main spar.
10/23/2004 Finished most ribs to main spar
10/24/2004 Cut and cleaned up angle for landing gear
10/25/2004 Trimed and rounded over the F-1 supports
10/30/2004 Went to Dillsburg for some 2024T3 .040. Cut out rear spar and cut out the 4130 plate for the landing gear
10/31/2004 Attempeted to bend the rear spar, not very successful.
11/1/2004 Completed drilling plates for landing gear.
11/3/2004 Started cutting ribs for vertical stabilizer
11/4/2004 Completed cutting and bending the ribs. Have made arangements to get the rear spar bent over the weekend.
11/5/2004 Drilled main ribs to bottom skin.
11/6/2004 Bent rear spar and the 1" by 2" u channel for the fusealage section. Drilled rear spar and 3/16" angle.
12/27/2004 Took some time off to let hands heal. Been working on the center section. Welding the main landing gear. Tearing down the 1835 vw engine for rebuild.  Messed up the crank yesterday trying to get the flywheel nut off.
12/27/2004 Bent more doublers. Started working on the nose ribs for the center section.
12/28/2004 Half the nose ribs are completed. Spend most of the time working on the outer two ribs to get the correct distance and alignment.
12/29/2004 After talking to Steve Bennet, was able to get the fly wheel nut off the crank, Put some touch up welds on the landing gear . Completed two more nose ribs.
01/03/2005 Worked on a couple of nose ribs.
01/04/2005 Worked one nose rib and main rib.
01/05/2005 Completed all ribs. Trimed rear F2's to size.
01/08/2005 Started working on left compression rib.
01/12/2005 Completed Left compression rib.
01/14/2005 Adjusted the left landing gear leg to allow the aileron push tube clearance to operate.
01/15/2005 Started working on the right compression rib.
01/17/2005 Adjusted the right landing gear to allow the aileron push tube clearence to operate.
01/18/2005 Completed Right compression gear.
01/19/2005 Started working on angles for forward section
1/21/2005 Purchased metal for Firewall.
1/22/2005 Completed Angles.
1/23/2005 Worked and completed Firewall and temporally bolted angles on.
1/25/2005 Started final riveting the M-1s to the firewall.
1/26/2005 Went to Dillsburg to pickup the axle tubing and tubing for the Nose gear.
1/27/2005 Cut axle to length and cleaned up.
2/2/2005 Worked on control setup.
2/5/2005 Cut plates and tubing for nose gear.
2/6/2005 Cut plates for tubing. 
2/11/2005 Corrected error with F-7C, too low. Took main landing gear and Firewall nosegear support to be welded.
2/12/2005 Worked with Bobby to complete 8050-1 to register the airplane. Inspected Ron's Mini for firewall ideas.
2/13/2005 Made copy of Tail Number paperwork to include with registeration and mailed it.
2/14/2005 Worked on brake setup for left main gear. Attached wings to determine locations to run pitol/static and lights tubing.
2/16/2005 Ron Dixon came up and inspected the bird. Worked on rod end connections.
2/18/2005 Finished one rod end adapter for ailerons.
2/19/2005 Finished 2nd rod end adapter and cut 2 rod end connectors and taped them.
2/28/2005 Trimed bottom skin. Pulled center section apart for final clean-up. Put final bolts in wing connections. Drilled last CS-13 for left rear wing connection. Received Registration for N853WD today.
3/5/2005 Worked on Elevator control. Cut and drilled trailing edge for center section.
3/6/2005 Cut access and worked on CS-20,21,22. Trimed control rod to length.
3/8/2005 Cut top skin to length.
3/11/2005 Started drilling Top skin to main ribs
3/12/2005 Completed Top skin. Drilled bottom main spar and bottom skin. Angled holes for wing connection points.
3/18/2005 Setup bending brake for nose skin. Bent nose skin and drilled main spar holes.
3/19/2005 Completed drilling nose ribs and nose skin. Have drilled holes for pitot/static tubes.
3/21/2005 Trimed up the nose skin. Completed some flex angle for two ribs for support when cutting for F-4's.
3/22/2005 Riveted flex angle to two ribs. Cut slots for F-1s and F-4s in nose skin.
3/23/2005 Cleaned up slots in nose skin. Drilled flex angle to nose skin. Dileed holes for electrical tubing. Placed grommets in all holes.
5/8/2005 After going to Sun-N-Fun and attending all of Steve Bennett's forums, I started working on the engine. Almost ready to start final assembly. Started working on the fuselage, cut bottom sheet and bent to shape.
06/19/05 Update to show how fusealage is coming along.
07/13/05 Update to Bulkheads, some firewall work, braces, bent nose gear tube, side panels for cockpit.
07/14/05 1st attempt to figure out the sheet metal for the top of the fusealage
07/23/05 Have first sheet between bulkhead C and D completed. Nose gear is welded up, now needs to be trimed. I can continue to do more with the plane now that I have completed my studies and passed the Project Managet test!
08/20/05 Had alot of other issues come up. Nose gear trimmed and pilot holes drilled for bolts. Started final assembly of fuselage braces. Plane on langing gear for the first time.
08/28/05 Bent 1/4 inch stiffener in bottom sheet. Started working on bottom of fuselage for final assembly. Finished drilling and counter sinking some of the holes.
09/18/05 Still working on the turtle deck and work on small detail stuff.
10/10/05 Figured out what was wrong with the turtle deck. Rebuilt the forms for Bulkheads 'D' and 'E', check out the new pictues which show how much I had to change them. Worked on the side braces and final riveted the right side.
10/11/05 Finished up the left side brace.
10/12/05 Rebuilt Bulkhead 'F'. Worked on turtle deck and got them to fit much better and the rear of the fusalage is still level.
10/16/05 Trimmed up turtle deck sheets. Started on mount point for horz. stab.
11/5/05 Reworked horz. stab ribs, bent bottom sheets. Drilled only a couple of holes and placed on tail for pictures.
11/12/05 Bobby, Ron and Jeff came to inspect my work. They liked what they saw.
11/19/05 Worked on the Instrument panel. Cut, drilled and bent the panel. Placed what instruments I could in the panel for now. Need to figure out what to do for the radio and transponder.
12/02/05 Worked on the ribs for the rudders and ready to bend.
12/04/05 Started worked on the ribs for the vertical stabilizers.
12/11/05 Finished ribs for the vertical stabilizer and rudders.
1/17/06 Have one Rudder and Vertical Stabilizer almost finished.
1/18/06 Drilled Vertical Stabilizer hinge and 3/4 in spar. Ready to start fitting on right side.
1/22/06 Started fitting right side vertical stabilizer and closing up right side of horizontal stabilizer.
1/23/06 Finished up left side of horizontal stabilizer.
1/25/06 Started working on left side vertical stabilizer.
1/29/06 Finished left side vertical stabilizer. Started connecting it to the horz stab.
2/4/06 Finished connection brackets for vertical stabilizers. Closed up vertical stabilizers.
2/5/06 Built left rudder.
2/7/06 Worked on elevator and trim tab. Completed trim tab.
2/11/06 Worked on elevator.
2/14/06 Worked on leading edge for horz. stab. Trimed, drilled, ready for final trimming
2/26/06 Status update. Worked rudder control. Blind nuts installed on Hor. Stab. Used scrap piece on front fuse to see how it fits. Worked on luggage comprtment, ready to cut out the door.
3/11/06 Status Update: Working on horz stab, final riveted most of the stab, working on the rear spar and hinge area. worked on mount points for vert stab and rudders. cleaned up elevator and ready for final assembly. Had an inspection by Bobby, Ron and Jeff.
4/13/06 Finished closing the rudders. Have not done much due to work and Sun-N-Fun. Talked to Ron about a support for the rod end on the elevator. Whipped one out today.
5/28/06 Have not done much due to work. Mainly doing detail work. Cleaned up firewall, left a lip to put sealer when final assembly. Drilled for side panels of cockpit. cleaned up fuselage for connection to center section. Installed doubler for antenna. Put in tubing for electrial and antenna wire for easy replacement. Final riveted turtle deck where possible. Remember the picture to the left of the turtle deck..
5/29/06 How to get a plane in and out of your basement!
7/3/06 Progress todate. Ribs for side skins from firewall to instrument panel. Top skin cut and drilled, still need to do the bottom sides. Figured out where I wanted the transponder and radio.
7/23/06 Progress todate. Side panels done and right side bottom skin.
9/16/06 Progress todate. Finally can begin to start on the plane again. Access panel for the bottom of the center section.
9/23/06 Started replacing rod end connectors, mine weren't really up to par. Had these done at a local machine shop. Also working on the engine, need a few little parts to close it up.
10/15/06 Now have Brakes. Needed to resolve this before I can start closing up the center section. The pictures will show how I got the brake pads to sit in the drum. Also show my brake handles, now where do I put them?? ;-)
10/29/06 Engine now closed up, once I hang it on the airframe, I can finish it and break it in. Built cable end connectors for the brakes, now need some longer brake wire. Think I'll put the brake handles to the front and have brake petals. Worked on mounting the radio and transponder, need to see how much room I have to build a fuel tank. It will have to be a glass tank to fit around the radio and transponder. A quick view of what the instrument panel will look like. Will have my GPS on the left side of the panel. Not bad for 3 years work.
11/4/06 Worked on engine mount jig. Didn't like the 1st attempt on the accessory case board, so redid it. Made sure the firewall board was drilled exactly by using the firewall to double check the drill holes. Going to pretty much try to keep the engine mount stock, also took in the fact that I'm using an accessory case. Used thread-all rod and two oak boards to insure rock sold jig. Need 4 more "fender" washers. Will start notching the tubes after that.
11/11/06 Worked on gas tank. Have rough shape and will fine sand to fit under the top skin. Checked out the foot arrangement and it seems to be ok. Checked to see how the canopy will look on the bird. Checked to make sure I had plenty of room for my head. It maybe 2 inches, not much after putting on headset.
11/26/06 Continue to work on gas tank. Drilled holes for rudder tubing on firewall. Created brace for rudder control linkage. Cut tubing for engine mount, ready to weld.
12/3/06 Finished gas tank, ready to start setting up for glassing. Worked on linkage for rudder tubing. Got engine mount to welder.
12/8/06 Stearing control horns from rudder rod cut and ready to weld. Created a one-off spacer to drill the spinner plates. Spacer lasted long enough to get all the holes drilled and then broke. Realized only got 5 bolts instead of 6. Did rough cut-out for prop and placed on engine to check everything out.
12/17/06 Received everything back from the welder. Only two items left to weld, 1/4" bolt and rod end connector for steering. Trimed center rudder rod for stearing. Trimmed engine mount to fit on firewall. No space at the 6 O'Clock position for a starter, beware you need the starter at the 12 O'Clock position. Put engine on for first time to get a look at spacing for everything.
1/18/07 Picture Updates. Rudder Linkage, Seat Belt placement, Rudder tips, top and bottom, Cut outs for Nav lights in wing tips. Fuel tank being looked at by fiberglass man.
1/21/07 Working on Nav Lights, put fuselage on and rudders to work on rear rudder controls.
2/21/07 Ah, the stuff I really don't like. Fiberglass work on wing tips, fuel tank and cowling. I used the squared pattern for the firewall and now have to create (that's get help) a cowling for it.
4/1/07 Showing updates on fuel tank, cowling, rudder control, elevator control and wiring.
8/1/07 Been tied up with work and getting instrument rating. Decided to redo the fuel tank and not make it quite so large. Working on brake setup. Had to shorten the pedals. The nail is to give me an alignment location for the brake cable.
8/4/07Finished brake pedals and adjustable cable tensioners. Set nose ribs and ran tubing for the pitot/static system and nav lights for the wings. Initial install of the quick disconnect for the tubing for the removable wings.
10/14/07Worked on Pitol/Static lines, convert final lenght to softer tubing to be able to route easier. Worked on fuel tank top and started glassing the changed sections, 1 layer, fiberglassed left rudder top with 1st layer of glass. Got a nice turn and bank indicator to put in the pannel. Started trimming the canopy down to a nice fit. Installed bearings for stick and rudder control.
10/25/07Worked on fuel tank top. Had to put a relief in the tank for the new turn and bank indicator. Cut a 2 liter soda bottle in half and used the top tapered portions to make the relief for the indicator. Looks like I have enough clearance and didn’t lose too much space in the tank. Need to work on the hard points for the fuel gauge and fuel filler.
03/04/08It's been a rough few months, way too much work. Replaced the original fuel tank, the new one has a cap of 17 gals. Installed the Anti collision light and tail light. Hooked them up to watch them flash. Have alot of the instrument panel wired, now it needs to be cleaned up. Bent tubing for canopy support. Now need to determine where to split the canopy for entry. Many other small items being worked on as I get free time.
04/06/08Drilled and installed nuts for rectifier. Decided to use angle for rudder tips, found out I really don't like working on fiberglass. Made shoulder harness bracket out of 4 pieces of .040. Received the tank and epoxy mix to put the bottom part on. Now to let it cure.
12/27/08Started getting back into working on the plane. Plumed the fuel line through the firewall. Wired the Instrument panel, need to run the lines from the engine through the firewall, including the alt and battery wiring. Worked on gasolator mounting. Found some automotive trim material to protect wiring and pitot/static lines. Created the throttle and elevator trim handles. Working with Styrofoam to build the tail cover. Wired the dimmer unit. Mounted the push to talk and transponder wires. Worked on brace for throttle cable.

Current Pictures
Latest at the Bottom


Return to top of page